Cleanrooms for semiconductors
It is the only sector that goes below ISO 5: in ISO 1 the limit is ten particles of 0.1 µm per cubic metre. It is not a tighter class than the others, it is another way of building a room.
- ULPA filtration U15–U17 — efficiency up to 99.999995 % at MPPS, against the 99.995 % at MPPS of an H14: penetration falls from 0.005 % to 0.000005 %, and below ISO 5 the latter is not enough
- Full-coverage ceiling and perforated floor — unidirectional flow crosses the whole floor plan at 0.3–0.5 m/s and returns as return air under the raised floor: it is this geometry that makes the class
- Molecular contamination under control — non-outgassing materials, chemisorbent filters and ppb sensors: below ISO 3 the problem is no longer just the particle, it is the molecules
- Climate at ±0.1 °C and ±1 % RH — because in photolithography a thermal drift becomes an overlay error, and an overlay error is scrap
- ISO 1–5Classes delivered for the sector
- 10 part./m³ISO 1 limit at 0.1 µm
- U15–U17ULPA filtration classes
- AuditAudit-ready documents, where required
Microelectronics, photonics, packaging and testing
They entrusted Phamm Engineering with the environments where work is done below the micrometre, from design to qualification.
Three classes, and between the first and the last
there are four orders of magnitude
The limits are those of ISO 14644-1 at 0.1 µm, and putting them side by side is the most honest way of saying what it costs to go down a class: between an ISO 5 and an ISO 1 the design does not change, the trade does.
-
ISO 1 10 part./m³ at 0.1 µm
Advanced lithography
The highest purity the standard classifies: resist exposure, extreme-ultraviolet lithography, processes where a single particle is worth a die. Full filter coverage and molecular control.
Advanced wafers -
ISO 3 1,000 part./m³ at 0.1 µm
Wafer fabrication
The fab standard: growth, oxidation, diffusion, deposition and etching. ULPA unidirectional flow over the whole floor plan and return under the floor.
Diffusion and deposition -
ISO 5 100,000 part./m³ at 0.1 µm
Testing and packaging
Electrical testing, wire bonding, encapsulation and metrology. The wafer is already processed: here the risk shifts from the particle to electrostatics.
Assembly and test
Six problems that semiconductors bring
and other sectors do not
Every item is a requirement with a number and a standard behind it. If a requirement has no measure, it is not a requirement.
-
Below ISO 5 a HEPA filter is no longer enough
An H14 stops 99.995 % at MPPS, the most penetrating particle diameter: excellent down to ISO 5, insufficient below. You need ULPA U15–U17, which stop 99.9995 % at MPPS, installed with sealed frames and verified on site — because at these efficiencies the leak is almost always in the frame, not in the medium.
-
A tenth of a degree becomes an overlay error
In photolithography the wafer, the optics and the machine expand differently, and the deviation ends up in the alignment between two layers. HVAC at ±0.1 °C and ±1 % RH, with the probe where the process is and not where it is convenient to put it.
-
Vibrations are fought by making the floor move
For lithography machines passive isolation is not enough: you need active platforms that measure ground motion and compensate it in real time. We prepare the structure so that those platforms can work — independent foundations, systems separated from the volume, site measurement before laying anything.
-
Molecules pass where particles stop
Airborne molecular contamination — acids, bases, condensables, organics — goes through a particle filter without noticing, and settles on the wafer. Non-outgassing materials, activated-carbon chemisorbent filters and monitoring with parts-per-billion sensors.
-
Everything in the room looks at the same earth
An electrostatic discharge on a device a few nanometres in size leaves no visible marks and is not found at functional testing: it is found in the field, months later. Conductive floors, ESD-safe furniture and single earthing according to IEC 61340-5-1, verified on the finished system.
-
The gas is as pure as the pipe that carries it
Nitrogen, argon and helium arrive ultra-pure and can degrade in the last ten metres. Electropolished steel pipework, orbital welds, inert-gas purge and purity analysis at the point of use: the declaration that matters is the one at the machine connection, not at the cylinder.
One particle, one die
A 300 mm wafer holds a few hundred dies, and each is a finished device. A particle that lands in the wrong place during one of the hundreds of process steps does not damage the wafer: it wipes out a piece of it, and that piece had already cost all the processing done up to that point.
That is why here the class is pushed where no other sector goes. And it is also why the choice of class must be made process by process: a room too clean for what is done in it does not increase yield, it only increases the bill.
- 10Part./m³ in ISO 1
- 1,000Part./m³ in ISO 3
- 100,000Part./m³ in ISO 5
Six steps, one point of contact
It is the same path across all ten sectors: what changes is what we look at at each step, not who answers.
-
01
Analyse
Process, standards and site constraints: from these come the class and the URS that sets it.
-
02
Design
Layout, separate flows, pressure cascade and HVAC, verified on BIM and CFD models.
-
03
Manufacture
Panels, metalwork and switchboards in our workshop, with factory acceptance testing (FAT).
-
04
Install
On-site assembly, systems and monitoring, on-site verification (SAT) and start-up.
-
05
Qualify
We carry out the tests and deliver audit-ready documentation, where required.
-
06
Support
Scheduled maintenance, filters and calibration, even on systems by others.
Where our cleanrooms end up
Six processes with requirements that differ from one another, and it makes no sense to take them all to the tightest class: each asks for its own, and the difference shows on the energy bill for the next twenty years.
-
Wafer fabrication
Crystal growth, thermal oxidation and diffusion: the phases where the wafer is bare and every particle counts.
ISO 1–3 -
Photolithography
Resist exposure, where climate and stability matter as much as the particle class.
ISO 1–3 -
CVD and PVD deposition
Thin films on substrate, with control of process gases and cross-contamination.
ISO 3 -
Plasma etching
Dry and wet etching, with control of molecular contamination from by-products.
ISO 3 -
Wire bonding and packaging
Chip assembly, bonding and encapsulation: here the dominant risk becomes electrostatics.
ISO 5 -
Electrical testing and metrology
Wafer probe, parametric testing and dimensional measurements, in a stable, vibration-free environment.
ISO 5
Below ISO 5 the standards that matter
become more numerous
To air classification are added the parts of ISO 14644 that concern molecular contamination and surface cleanliness, EN 1822 which defines what a U17 really is, the IEC for electrostatics and the SEMI standards that machine manufacturers take for granted.
- ISO 14644-1
- ISO 14644-2
- ISO 14644-3
- ISO 14644-4
- ISO 14644-8 · AMC
- ISO 14644-9
- EN 1822 · H13–U17
- IEC 61340-5-1
- SEMI F
- SEMI E
What they ask us before signing
The six questions that come back at every site survey, with the answer we would give in person.
Which ISO class is needed for semiconductors?
It depends on the process, and the right answer is almost never «the tightest». Wafer fabrication and lithography sit in ISO 1–3; packaging, bonding and testing are fine in ISO 5. Taking the whole fab to the class of the most critical process is the most expensive mistake that can be made in design: treated air is paid for every hour for twenty years, and an over-specification does not raise yield by a point.
What is the difference between HEPA and ULPA?
An H14 retains 99.995 % at MPPS, the most penetrating particle diameter, and is the right choice down to ISO 5. A ULPA U15–U17 retains 99.9995 % at the same MPPS, and below ISO 5 it is not an alternative but a requirement. Beware of installation: at these efficiencies the leak is almost always in the frame, so the tightness of the frame and the in-situ integrity test matter more than the filter’s datasheet.
How is molecular contamination controlled?
AMC — acids, bases, condensables, organics — passes through a particle filter without being retained. It is controlled on three fronts: non-outgassing materials for panels, sealants and finishes; activated-carbon chemisorbent filters on supply and recirculation; monitoring with parts-per-billion sensors, because without a measurement you do not even know whether the problem exists.
How long does it take to build?
An ISO 5 room for testing and packaging takes 12–16 weeks from design to qualification. A fab in ISO 1–3 takes 24–36 weeks, with the BIM model, CFD simulations, gas distribution and qualification included. It is the longest build in our range, and the detailed schedule is already in the quote.
Can an existing cleanroom be converted or upgraded?
Yes, and it is an important part of our work: filtration upgrades, moving to a tighter class, adding molecular control or ESD systems, layout reconfiguration. We also work on systems built by others, with a dedicated technical site survey: first we measure what the room does today, then we decide what is worth changing.
Do you provide maintenance after commissioning?
Yes: ULPA filter replacement, periodic ISO 14644 recertification, in-situ integrity tests, sensor calibration and HVAC performance checks. On a system that stops, response time matters more than anything else, and we agree it in writing together with the maintenance contract.
Tell us what processes will go inside, not just how many square metres
Processes to host and the class each requires, machines with their footprints and utilities, process gases. With these three elements the quote is accurate first time, built on your process.
- IT+39 02 8364 7535
- ES+34 673 889 559
- info@phammeng.com